Barro Group behind schedule

Residents’ hopes that the end of underground fires that have been burning for nearly three years at the Kealba Landfill could be nearly over have been dashed.

The Barro Group, which runs the landfill, has submitted an application to the Environmental Protection Authority asking for an extension to the deadline given for the fires to be out.

The current deadline is August 22, but EPA told residents at a community meeting last week, that they have fallen behind schedule.

Residents were told the Barro Group wants an extension until February to have the last hot spot out. The EPA originally gave Barro until July last year to have all the fires out.

The EPA must assess the submission and will decide whether it will be accepted.

EPA chief executive Lee Miezis says the organisation is on the community’s side with this issue and the response from Barro Group is unacceptable.

He said they were unsure if penalties would be imposed on the Barro Group.

“Our interest is in making sure this company is doing absolutely everything they can to put these hotspots out as quickly and safely as possible,” he said.

“We’ll assess [Barro Groups extension application] as we are required to do so under law but our interest is if they have done everything they can that they need to do for us to be satisfied. If they haven’t, then there will be an escalation and enforcement action by the authorities.”

At the community meeting, the EPA advised they may see an increase in odour reports and the intensity of the smell in the coming weeks.

Residents have long complained about odours coming from the side and the impact it’s had on their physical and mental health.

Brimbank councillor and affected resident Virginia Tachos said this latest application for extension is yet another blow to the community with this ongoing disaster.

“People have really been suffering with worsening odour and been told to just ‘leave their home’ by the EPA when it gets really bad.

“Highly insensitive and patronising comments don’t help – the EPA should be protecting us from the odour.”

Barro’s license is currently suspended by the EPA meaning they can’t take waste.

As reported by the Star Weekly, the Barro group said in June they were unsure whether they would reopen the site once the fires were out.

Digital Editions


More News

  • Getting ready for kindergarten

    Getting ready for kindergarten

    As part of ‘kindergarten readiness month’ next month, local sessional kindergarten providers will host a series of open days from 17-26 March, giving families the chance to explore local kindergartens.…

  • Braybrook ramps up for BMX fest

    Braybrook ramps up for BMX fest

    Purchase this photo from Pic Store: 532725 Melbourne’s inner-west will take centre stage this weekend at the Braybrook BMX Festival, a three-day celebration of action sports, youth culture and community,…

  • Brimbank writers and readers festival returns

    Brimbank writers and readers festival returns

    Lovers of literature rejoice! The Brimbank Writers and Readers Festival is returning next month for its biggest event to date. Thirty-four events will run over six days, from 12-17 March,…

  • Former Cash Converters operators penalised

    Former Cash Converters operators penalised

    The Fair Work Ombudsman (FWO) has secured a total of $112,985 in penalties against the former operators of three Cash Converters stores in Melbourne’s north and west. The Federal Circuit…

  • Cougars finals hopes take a hit

    Cougars finals hopes take a hit

    Purchase this photo from Pic Store: 532911 Sunshine YCW’s hopes of playing finals suffered a setback on Saturday in the Victorian Turf Cricket Association Clark Shield. Hoping to regain its…

  • NFL coming to Melbourne

    NFL coming to Melbourne

    Purchase this photo from Pic Store: 178232 The National Football League has confirmed that the San Francisco 49ers will play the Los Angeles Rams at the Melbourne Cricket Ground in…

  • New

    New

    Nearly 1000 new doctors are entering Victoria’s public health system this month, with a significant number allocated to hospitals serving Melbourne’s western and northern growth corridors. Among the 965 medical…

  • Cancer researchers supported

    Cancer researchers supported

    The next generation of cancer research leaders are being supported through a four-year cancer research fellowship program, supported by the state government. Health Minister Mary-Anne Thomas has announced the inaugural…

  • Support Sweethearts for HeartKids

    Support Sweethearts for HeartKids

    Every day in Australia, eight babies are born with a childhood-onset heart disease (CoHD), and this February HeartKids is calling on Australians to help support these children and their families…

  • Walk to Work Day coming

    Walk to Work Day coming

    The Pedestrian Council of Australia has announced a new initiative for Walk to Work Day, partnering with the Black Dog Institute to highlight the mental health benefits of walking. The…